PMP Question of the Day...

Today's question is from the Stakeholder Management Process Group. Which of the following is an input to the Identify Stakeholders process?

A. Project management plan
B. Analytical techniques
C. Project charter
D. Project scope

Ref: PMBOK® Guide, Fifth Edition, Section 13.1, Page 393