Tuesday, September 24, 2013

PMP Question of the Day...

Walter is developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle. Which of the following processes does this define?

A. Control Stakeholder Engagement
B. Manage Stakeholder Expectations
C. Plan Stakeholder Management
D. Conduct Stakeholder Analysis

Ref. PMBOK® Guide, Fifth Edition, Section 13.2, Page 391

Monday, September 23, 2013

PMP Question of the Day...

Today's question is from the Stakeholder Management Process Group. Which of the following is an input to the Identify Stakeholders process?

A. Project management plan
B. Analytical techniques
C. Project charter
D. Project scope

Ref: PMBOK® Guide, Fifth Edition, Section 13.1, Page 393

PMP Certification Requirements

The Project Management Institute (PMI) is the sole organization that bestows the coveted Project Management Professional (PMP) Certification. We've put together the information that details the current qualifications and the cost to apply for the PMP Certification.

If you'd like to see if you're eligible, check HERE. There's also a link to download your FREE .pdf copy of the new PMBOK® Guide, Fifth Edition.

Sunday, September 22, 2013

PMP Question of the Day...

Today's question comes from the Planning Process Group. This involves a formula you need to remember when you take your PMP Certification Exam.

Marvin is managing a new project involving a software development product. On an average day, his coding staff can write 500 lines of code in 6 hours. On hectic days with a lot of interruptions and team meetings, they require 8 hours to write the same amount of code. On a good day, with no distractions, their performance results in 500 lines of code in 4 hours. Using the Beta Distribution method of three-point estimating, what estimate can Marvin use to enter his activity estimates going forward?

A. 7
B. 6
C. 5
D. 8

Please leave a comment with your answer and we'll see how many know the formula.

Ref: PMBOK® Guide, Fifth Edition, Section 6.5.2.4, Page 171

Saturday, September 21, 2013

Discount on our NEW PMP PROGRAM

We couldn't think of a better approach to kick off the new quizzes, tests, and exams included in our COMPLETE PMP CERTIFICATION PROGRAM than to reduce the price. And that's exactly what we've done. From now until December 31, 2013, our program is discounted from our regular $199 to a year-end bargain basement price of only $49. You still get 12 months of unlimited access to everything on a 24/7 basis.

In return for such a great deal, we're hoping you can help us work out the glitches, if there are any. The project of revising our entire Question Library was a massive one. We hope it's perfect, and we also hope you'll send us a comment if you encounter a typo. If you already have your PMP Certification, feel free to pass our information along to an associate.