Walter is developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle. Which of the following processes does this define?

A. Control Stakeholder Engagement
B. Manage Stakeholder Expectations
C. Plan Stakeholder Management
D. Conduct Stakeholder Analysis

Ref. PMBOK® Guide, Fifth Edition, Section 13.2, Page 391